Archive for the 'Shilshole Marina' Category

Dec 09 2019

Security Phone Numbers

These numbers are posted on each gate and everyone should have these in their phone.  Please save this image to your phone or take a picture of the one on the gates.  There is also a link on the right side of this page.  And, as always, if you see something, say something!  

No responses yet

Nov 02 2019

Construction Update-Nov. 1

Bi-Weekly Update:

M3 foundation; photo courtesy of Gary Peterson, E-dock

New M3 Building
• Under slab utility installation complete and working on rebar installation.
New M4 Building
• Under slab utility installation continues.
New M6 Building
• Completed excavation, sub grade passed, and starting backfill.

Looking Ahead:
New M3 Building
• Continue with rebar installation and prep for slab placement
• Start building installation.
New M4 Building
• Continue with installation of utilities.
• Start installation of forms for slab on grade.
• Start installation of rebar.
New M6 Building
• Place base course and test for compaction.
• Start installation of under slab utilities.

Please contact the marina office at 206-787-7236 for further information or send an email to
Shilshole-Outreach@portseattle.org

restroom project and plans

No responses yet

Oct 16 2019

Construction Update 10-15-19

Construction Update 10-15-19

 

photo courtesy of Gary Peterson

No responses yet

Oct 09 2019

Construction Update- October 8

Published by under Shilshole Marina

Customer Service Facilities
(Restroom Project)
Construction Update- October 8, 2019

This Week:
o M-3 South Restroom
• Site excavation is finished
• Slab-forming and under-slab utilities installation is underway

o M-4 Central Restroom
• Pre-excavation activities are in progress, including soil-sampling, erosion control, asphalt saw-cutting and temporary jobsite power.

o M-6 North Restroom
• Parking spaces within the building site have been posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 10th
o Construction fencing will be set up around the M-6 North Restroom building site on early on October 14th

Please contact the marina office at 206-787-7236 for further information or send an email to
Shilshole-Outreach@portseattle.org

No responses yet

Oct 02 2019

Construction Update- October 1

Published by under Shilshole Marina

This Week:
o M-3 South Restroom
• Excavation nearing completion
• Slab forming and in-slab utilities installation to begin

M3 excavation, photo courtesy of Gary Peterson

o M-4 Central Restroom
• Construction fencing erected on October 3rd
• Pre-excavation activities (soil sampling, erosion and sedimentary controls)

o M-6 North Restroom
• Parking spaces within the building site posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 12th
o Construction fencing will be set up around the M-6 North Restroom building site on October 14th

Please contact the marina office at 206-787-7236 for further information.

No responses yet

Next »