Nov 02 2019
Construction Update-Nov. 1
Bi-Weekly Update:

M3 foundation; photo courtesy of Gary Peterson, E-dock
New M3 Building
• Under slab utility installation complete and working on rebar installation.
New M4 Building
• Under slab utility installation continues.
New M6 Building
• Completed excavation, sub grade passed, and starting backfill.
Looking Ahead:
New M3 Building
• Continue with rebar installation and prep for slab placement
• Start building installation.
New M4 Building
• Continue with installation of utilities.
• Start installation of forms for slab on grade.
• Start installation of rebar.
New M6 Building
• Place base course and test for compaction.
• Start installation of under slab utilities.