Construction Update- October 8

Published by at 8:02 pm under Shilshole Marina

Customer Service Facilities
(Restroom Project)
Construction Update- October 8, 2019

This Week:
o M-3 South Restroom
• Site excavation is finished
• Slab-forming and under-slab utilities installation is underway

o M-4 Central Restroom
• Pre-excavation activities are in progress, including soil-sampling, erosion control, asphalt saw-cutting and temporary jobsite power.

o M-6 North Restroom
• Parking spaces within the building site have been posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 10th
o Construction fencing will be set up around the M-6 North Restroom building site on early on October 14th