Sep 24 2019
Construction Update
SHILSHOLE BAY MARINA
Customer Service Facilities
(Restroom Project)
Construction Update- September 24, 2019
This Week:
o M-3 South Restroom building site:
• Test holes have been dug for environmental testing on dirt for proper disposal
• Tentative time frame to start excavating site depends on results for environmental testing
o M-4 Central Restroom:
• Construction fencing will be set up October 3rd
• Erosion control measures will set up after fencing is in place
• Excavation is expected to start October 8th
Looking Ahead:
• Signs will be posted for M-6 North Restroom announcing “No Parking after 10pm October 12th”
• Construction fencing will be set up around the M-6 North building site
Please contact the marina office at 206-787-7236 for further information or send an email to Shilshole-Outreach@portseattle.org