Oct 02 2019

Construction Update- October 1

Published by at 11:11 am under Shilshole Marina

This Week:
o M-3 South Restroom
• Excavation nearing completion
• Slab forming and in-slab utilities installation to begin

M3 excavation, photo courtesy of Gary Peterson

o M-4 Central Restroom
• Construction fencing erected on October 3rd
• Pre-excavation activities (soil sampling, erosion and sedimentary controls)

o M-6 North Restroom
• Parking spaces within the building site posted with “No Parking After 10/12”

Looking Ahead:
o At M-4 Central, excavation will begin on October 12th
o Construction fencing will be set up around the M-6 North Restroom building site on October 14th

Please contact the marina office at 206-787-7236 for further information.